Jiangsu Weifeng Power Industry Co., Ltd. Lithium ion Power Battery Project Purification Electromechanical General Contractor

Construction period: January 17, 2022 to April 27, 2022

Building area: 72000 ㎡

Clean area: 33000 ㎡

Cleanliness level:/

Category:
 
 

Contracting scope: including but not limited to all color steel plate partitions, air shower rooms, cargo shower rooms, color steel plate ceilings, clean doors, clean windows, purification electromechanical engineering, process electromechanical installation engineering (secondary distribution), NMP recovery system, etc. in individual buildings such as 2 # electrode assembly plant, chemical equipment plant, distribution plant, module plant, guard room 4, machinery repair shop, sewage treatment plant, etc NMP、 Engineering deepening design (providing BIM models), construction, equipment procurement, supply, installation, and commissioning of electrolyte material conveying system, dehumidification unit, air conditioning system, air compression system, refrigeration system, steam system, dust removal system, vacuum system, etc. (not limited to these). All doors on the exterior walls of individual buildings shall be numbered with stainless steel and comply with the relevant requirements in the technical specifications.

Project Highlights: The Yancheng Power Battery Project is an important component of the "600" strategy of Beehive Energy, and a key step in the production capacity layout of Beehive Energy's large base in the Yangtze River Delta region. Honeycomb Energy will gather high-quality talents and material resources, formulate preferential policies, use advanced technology production equipment, scientifically plan park production bases, establish a century old green and environmentally friendly enterprise, meet the employment needs of local people, and promote the prosperity and development of the local economy in Yancheng.



Aerial view

 

 